In Osterweddingen near Magdeburg, the energy transition is entering the next phase: a hydrogen plant is currently being built in the local industrial park, which will enable local industrial companies to obtain green hydrogen in future.

In the first stage of expansion, around 900 tonnes of green hydrogen per year will be produced using a 10 MW PEM electrolyser. The electrolyser will be operated to support the system in order to compensate for fluctuations in the generation of electricity from wind and solar power and thus reduce the load on the electricity grid.

The green hydrogen will be used to decarbonise industry, as a fuel for long-haul transport, to feed into hydrogen pipelines and, in the long term, to generate electricity during a ‘dark lull’.

Project profile
Location: 
Osterweddingen (near Magdeburg)
Power class: 
10 MW
Commissioning: 
2025
H2 volumes: 
900 t/a
Delivery concept: 
Trailer fleet (bis 380 bar)
ELLERYSTUDIO-2307-Enertrag-Infografik-Osterweddingen-01.jpg
« L'hydrogène est un élément indispensable à la transition énergétique et offre des solutions pour décarboner différents secteurs, de l'industrie lourde au transport longue distance. En étant directement relié à nos parcs éoliens et solaires à proximité, cet électrolyseur produira non seulement de l'hydrogène vert, mais favorisera également d'autres implantations industrielles dans la région et augmentera la valeur ajoutée locale. ».

Dr. Tobias Bischof-Niemz

ENERTRAG Comité directeur Projets International & Technologie

Enertrag DT_Drohne - JEWRO LR-58.jpg
Enertrag DT_Drohne - JEWRO LR-58.jpg
Enertrag DT_Drohne - JEWRO LR-58.jpg
Enertrag DT_Drohne - JEWRO LR-58.jpg

About ENERTRAG

As an independent energy company, ENERTRAG generates electricity and heat exclusively from renewable sources and supplies secure, affordable renewable energy for all areas of life. With over 30 years of experience, ENERTRAG combines all the expertise required for successful operation and efficient maintenance, for citizen-centered planning, reliable construction of energy plants and grids through to complete integrated power plants. 

Learn more

Flagship projects

The goal: 100 percent fossil-free – worldwide. To achieve this, ENERTRAG is turning pioneering ideas into sustainable, viable solutions.

ETAPA 4 ZONA 1-2_Moment2.jpg

Hyphen : Projet d'hydrogène vert en Namibie

Puissance nominale 3.5 GW
En service depuis
Emplacement Namibia
Statut TBA

Hyphen : Projet d'hydrogène vert en Namibie

Sur environ 4.000 km2, ENERTRAG réalise le projet Hyphen dans le parc national de Tsau/Khaeb : Le premier projet d'hydrogène vert namibien entièrement intégré verticalement à l'échelle du gi...

ENERTRAG_Spatenstich_Elektrolyseur_Osterweddingen_20240513v4.jpg

Osterweddingen hydrogen plant

Puissance nominale 10 MW
En service depuis 2025
Emplacement Osterweddingen
Statut en construction

Osterweddingen hydrogen plant

A hydrogen plant in Osterweddingen near Magdeburg will supply local industries with green hydrogen. A 10 MW PEM electrolyser will produce 900 tonnes annually, stabilizing the grid by balanc...

PV Uckermark_ Enertrag LR-36.jpg

Le parc photovoltaïque de Kreuz, dans l’Uckermark

Puissance nominale 20 MW
En service depuis 2023
Emplacement Gramzow
Statut en service

Le parc photovoltaïque de Kreuz, dans l’Uckermark

Le parc solaire de Kreuz produit 20 millions de kWh par an et dispose d'une batterie de 3,4 MW pour la stabilité du réseau et l'alimentation d'urgence

Bild3.png

Battery storage Tantow

Puissance nominale 60 MW / 120 MWh
En service depuis 2026
Emplacement Tantow
Statut prévu

Battery storage Tantow

The Tantow battery storage facility (60 MW, 120 MWh) will stabilize the grid by storing surplus renewable energy and supplying it when needed. Built on 1 hectare with 32 battery containers, ...

Enertrag_Windpark_23 JR_HR-217.jpg

Le parc éolien de Dunowo en Pologne

Puissance nominale 186 MW
En service depuis 2021
Emplacement Pologne
Statut en service

Le parc éolien de Dunowo en Pologne

C’est l’un des plus grands projets éoliens sur le sol polonais : avec le projet Dunowo, ENERTRAG a mis en service son plus grand projet à ce jour.

TZZS5378.jpg

Corridor d'électrolyse dans l’est de l’Allemagne

Puissance nominale 185 MW Elektrolyse
En service depuis
Emplacement Allemagne
Statut en construction

Corridor d'électrolyse dans l’est de l’Allemagne

Les projets intégrés et interconnectés sont la seule voie vers une économie de l'hydrogène performante en Allemagne et en Europe. C'est exactement ce vers quoi tend le projet d’ENERTRAG "Cor...

Concrete Chemicals

Puissance nominale 35 kt/a SAF
En service depuis 2028
Emplacement Rüdersdorf
Statut prévu

Concrete Chemicals

Le projet phare innovant Concrete Chemicals est considéré comme un jalon de la décarbonisation de l'aviation.

La centrale de référence en Lusace

Puissance nominale 12 MW
En service depuis
Emplacement Lausitz
Statut prévu

La centrale de référence en Lusace

Programme de soutien aux laboratoires de la transition énergétique .

Les rails de l’avenir écologique

Puissance nominale 4 MW
En service depuis
Emplacement Rüdersdorf
Statut en construction

Les rails de l’avenir écologique

Quand l'hydrogène vert nous fait avancer.

Tambores_15_-_Foto_600.png

Tambor : E-méthanol à partir d'hydrogène vert

Puissance nominale 350 MW
En service depuis
Emplacement Uruguay
Statut prévu

Tambor : E-méthanol à partir d'hydrogène vert

ENERTRAG planifie le Tambor Green Hydrogen Hub dans le département de Tacuarembó, Uruguay.

News

Stay up to date with the latest articles from the press area

Visuel-pour-article-Site-Enertrag-1-1-843x675.png

ENER’MAG n°20

Contact

Fields
Cloudflare Turnstile Captcha

J'autorise le traitement de mes données personnelles conformément à la déclaration de confidentialité. J'ai lu et compris la .déclaration de protection des données