ENERTRAG SE is planning the construction and operation of a 4 MW class wind turbine in Ramelsloh in the municipality of Seevetal. The planned and approved turbine is a VESTAS V150 with an output of 4.2 MW and a hub height of 125 meters.
The exact location for the construction of the wind turbine is on the eastern side along the Ohlendorfer Weg within the VRG SE_03 Ramelsloh wind priority area. Construction is expected to start in the fall of 2023 and the turbine is scheduled to be erected and commissioned in early 2024.
ENERTRAG provides all services related to renewable energies. We efficiently combine electricity, heat and mobility in all areas of life. As an energy producer with an annual production of 1.38 million MWh in our portfolio, 772 installed turbines and a "PowerSystem" service network with 1072 monitored wind turbines, we know from our own experience what is important to our customers.
With over two decades of experience in Europe, our 780 employees combine all the skills required for successful operation and efficient maintenance, citizen-oriented planning, reliable construction of energy plants and grids through to complete integrated power plants. We are always one energy ahead - be it in sector coupling, participation models or demand-oriented night-time marking.
12/20/2021
After a two-and-a-half-year approval procedure, the BImSch permit for the construction of a V150-4.2 MW wind turbine with a hub height of 125 m, a total height of 200 m and a rotor diameter of 150 m from the manufacturer Vestas was granted on 20.12.2021.

Image: Site plan of the Ramelsloh wind project
The project team is looking forward to the next steps and preparations as well as continued good cooperation with the local community. Once all planning has been completed, the construction phase will begin in fall 2023, with commissioning expected in early 2024.

“Energy policy is a question of industry policy, security policy, future policy and environmental policy. ENERTRAG Verbundkraftwerke® provide a reliable, plannable and cost-effective supply of energy, thus laying the foundations for what a strong economy needs, namely import independence, in-country value creation, jobs and the energy crucial to innovation. There can be no data centres without electricity, no industry without a reliable supply. Far from being a mere side-effect of all this, lower carbon emissions are the result of the right decisions being made.”
Dr. Anne Bendzulla
ENERTRAG Member of the Executive Board responsible for the Power Generation division
The development of a site is of essential importance, as the realization of the project is not possible without secure access.
First of all, it is also important to differentiate between development and construction traffic. The former relates to traffic for the ongoing operation of the wind turbine (fire department, maintenance vehicles, police, etc.). This traffic to the wind turbine must be adequately secured for the entire service life of the turbine. The latter concerns traffic for the construction of the wind turbine, which includes construction site traffic (concrete mixers, trucks) as well as sword transports for the delivery of the turbine components. This only needs to be secured at certain points and is irrelevant for the development.
Access traffic is carried out via the publicly dedicated road network of the municipality of Seevetal. The plant site can be accessed directly via Ohlendorfer Weg.
Some of the construction traffic and construction site traffic will take place via Buchwedelweg and delivery of the components is planned via the Seevetal-Ost highway service area due to the oversized size of the heavy goods vehicles.

The planning and development of wind projects are time-consuming and require a great deal of commitment and perseverance. On average, the development of a wind energy project takes around 7 years. The following key phases can be identified:
Land acquisition: from 2017 until today
Approval planning: from February 2019 to December 2021 (receipt of BImSch approval)
Construction phase Construction of the wind turbines and laying of the cable route: expected to take 6 months from fall 2023
Operation: 20 years by ENERTRAG
The entire construction phase is expected to take 6 months. Various factors such as weather conditions can have a negative impact on the processes and delay the project considerably. The construction phase is divided into various sections:
Construction preparation: tree care, approx. 1 week
Road construction: Temporary development of the paths for construction traffic, approx. 2/3 weeks
Foundation work: excavation, concrete pouring and curing, approx. 4 weeks
Installation: Erection and commissioning of the system. Approx. 2 weeks.
The cable route is laid at the same time.


ENERTRAG produces renewable energy in a sustainable way, to keep the Earth habitable. Together. With passion. Energy ahead.
The system will go into operation in compliance with emission regulations and will not exceed a maximum sound power level of 106.6db(A) at full load. At night (22h-6h) the plant will be operated in noise-reduced mode. The maximum sound power level will not exceed 105.1dB(A).
The construction of a wind turbine must always be considered as an intervention in nature and the landscape. The Federal Nature Conservation Act ensures that these interventions are compensated for by the implementation of compensation and replacement measures, which is known as the compensation obligation.
In close coordination with the UNB, ENERTRAG will implement 2 compensation measures in Ramelsloh.
The first compensatory measure concerns the creation of lark boxes. Due to the lack of suitable breeding sites for the skylark, this species has been considered particularly endangered since the 1980s. Intensively used arable land offers fewer and fewer free landing places for the skylark and the densely planted cereals are not suitable for sufficient insect food. By creating skylark windows, areas are created where the skylark can find landing and breeding sites as well as sufficient food. Specifically, skylark windows are deliberately created gaps in agricultural land. The 20 square meter windows are mainly created in cereal fields or rapeseed fields of at least 5 hectares. Two lark windows per hectare are sufficient for the animals and the crop loss remains minimal.
A shrub hedge will be planted to compensate for the adverse effects on the ecosystem caused by construction and planting. To compensate for the removal of trees and shrubs over a length of 9 m, an equivalent bitotope of the type "shrub hedge" will be planted elsewhere. The measure will be carried out as a 3-row planting of shrubs from native, site-appropriate species of regional origin. (e.g. hawthorn, blackthorn, hazel, Pfaffenhut etc.).

ENERTRAG uses its 30 years of experience worldwide to accelerate the transition to renewable energies.

ENERTRAG has been planning a new, regionally significant energy project for several years, for which a separate approval procedure with public participation is to be carried out. Transparent...

ENERTRAG has been planning a wind field south of Penkun for several years, for which a separate approval procedure with public participation is to be carried out. In this context, transparen...

ENERTRAG, wpd and naturwind are planning a new, regionally significant energy project for which a separate approval procedure with public participation will be carried out. The following pag...

Bürgerwind Schönfeld UG & Co. KG initially plans to operate two Vestas V117 wind turbines, each with a rated output of 3.45 MW and a total capacity of 6.9 MW, known as the Schönfeld III proj...

Bürgerwind Matteshöhe UG & Co. KG operates 4 GE 3.6-137 wind turbines with 3.63 MW and a total installed capacity of 14.52 MW in the municipalities of Uckerfelde and Grünow (Brandenburg).

ENERTRAG has been planning a wind field north-east of Ramin for several years, for which a separate approval procedure with public participation is to be carried out. The following pages are...

ENERTRAG Windfeld Schönfeld III GmbH & Co. KG plans to operate 5 Vestas V117 wind turbines, each with a rated output of 3.45 MW and a total capacity of 17.25 MW, known as the Rosow wind fiel...

The “Dauer III” and “Dauer IV” wind project is located in the north-east of Brandenburg, east of the Prenzlau district of Dauer. The environmentally friendly construction and operation of th...

ENERTRAG has been planning a new, regionally significant energy project for several years, for which a separate approval procedure with public participation is being carried out. In this con...

ENERTRAG SE is planning the construction and operation of a 4 MW class wind turbine in Ramelsloh in the municipality of Seevetal. The planned and approved turbine is a VESTAS V150 with an ou...

ENERTRAG is planning to erect two wind turbines in the outskirts of Iserlohn, between Gerlingsen and Kalthof. Due to the 1,000 m distance regulation to residential areas stipulated in the st...

ENERTRAG is planning to erect three wind turbines on the outskirts of the municipality of Nordkirchen, on Münsterstrasse at Meinhövels Holz/Piekenbrock and to the west of the district of Cap...

CHEMIN DE TULERAS

SAINT-ANDRÉ-FARIVILLERS

CAMPREMY-BONVILLERS

CHEMIN-BLANC

DEMI-LIEUE

ROINVILLE

ORESMAUX

FRESNOY-AU-VAL

BOUGAINVILLE


LIANCOURT

REMIGNY-LY-FONTAINE

LA BRIE CHAMPENOISE

The Anguilcourt wind farm, commissioned in 2016 and located in the Hauts-de-France region, comprises 6 Senvion wind turbines with a total output of 12 MW.

SISSY-MÉZIERES

SOUTH TERNOIS

TERNOIS EST

CROISETTE I

CROISETTE II

LA VILLE-AUX-BOIS-LÈS-DIZY

TERNOIS NORTH
Further information on the processing of your personal data can be found in our privacy notice.