State of development
The planning and development of wind projects are time-consuming and require a great deal of commitment and perseverance. On average, the development of a wind energy project takes around 7 years. The following key phases can be identified:
Land acquisition: from 2017 until today
Approval planning: from February 2019 to December 2021 (receipt of BImSch approval)
Construction phase Construction of the wind turbines and laying of the cable route: expected to take 6 months from fall 2023
Operation: 20 years by ENERTRAG
The entire construction phase is expected to take 6 months. Various factors such as weather conditions can have a negative impact on the processes and delay the project considerably. The construction phase is divided into various sections:
Construction preparation: tree care, approx. 1 week
Road construction: Temporary development of the paths for construction traffic, approx. 2/3 weeks
Foundation work: excavation, concrete pouring and curing, approx. 4 weeks
Installation: Erection and commissioning of the system. Approx. 2 weeks.
The cable route is laid at the same time.